Project name: Rollie Stool, drawings 1-5 of 22
Here is another project I need quotes on. I need the pieces fabricated and welded, and those welds ground. All pieces must be finished to a "brush" finish, which we achieve with 60 grit, then 80 grit, then red scotch bright, which gives a stainless brush look. However you get that look is fine with us. Additionally, if we would like the quote to include clear gloss powder coating (if you have that resource available) and shipping to 10022.
I need quotes for 2 (two) and for 20 (twenty) assemblies, minus the seat. Tell us how long you need to get it done. Please include project name in quote.
We will supply the bearings and the spring.
Additionally, we would be looking for someone to make 2 right away (within two weeks), so let me know ASAP if you have that ability.
***SEE FOLLOWING POSTS FOR ADDITTIONAL DRAWINGS. TOTAL OF 22 DRAWINGS*****
Here is another project I need quotes on. I need the pieces fabricated and welded, and those welds ground. All pieces must be finished to a "brush" finish, which we achieve with 60 grit, then 80 grit, then red scotch bright, which gives a stainless brush look. However you get that look is fine with us. Additionally, if we would like the quote to include clear gloss powder coating (if you have that resource available) and shipping to 10022.
I need quotes for 2 (two) and for 20 (twenty) assemblies, minus the seat. Tell us how long you need to get it done. Please include project name in quote.
We will supply the bearings and the spring.
Additionally, we would be looking for someone to make 2 right away (within two weeks), so let me know ASAP if you have that ability.
***SEE FOLLOWING POSTS FOR ADDITTIONAL DRAWINGS. TOTAL OF 22 DRAWINGS*****